PROCESS

HOW IT WORKS
DAY 1 Start 11h00 Finish 17h00
STEP 1
moladi formwork is delivered to site. Area = 74m² Mass = 550kg Volume = 4m³ moladi formwork panels are assembled by unskilled labourers to form the mould panels of the desired house plan.
STEP 2
Internal formwork panels are erected. Window frames and block-outs are positioned within the wall cavity. Reinforcing bars are positioned within the cavity to engineer specifications
STEP 3 •	Door frames and block-outs are positioned within the wall cavity.  •	External formwork panels are erected to  close off the wall cavity.  •	Erection is completed in 4 hours  with 4 unskilled labourers
STEP 4
The wall cavity is filled with 4m³ of moladi aerated mortar by unskilled labourers. The pour is completed in 2 hours with 4 unskilled labourers.
DAY 2 Start 07h00 Finish 17h00 STEP 5
moladi formwork panels are removed. moladi formwork panels are completely removed in 2 hours with 4 unskilled labourers.
STEP 6
Immediately after the formwork panels are removed, the walls are painted with cementitious water based paint. Oil or acrylic based paints can be applied after the walls have cured, or in 28 days.
STEP 7
The engineer certified roof is installed. The windows and doors are installed. Final finishing’s, such as sanitary ware and lighting are completed. The structure is now ready for occupation.
ADDRESS PO Box 16553 Emerald Hill Port Elizabeth South Africa 6011
CONTACT Mail: click here Phone: +27 413792600 Fax: +27 865026930
Copyright reserved © Terms of use apply

PROCESS

HOW IT WORKS
NAVIGATION
SOCIAL
DAY 1 Start 11h00 Finish 17h00
STEP 1
moladi formwork is delivered to site. Area = 74m² Mass = 550kg Volume = 4m³ moladi formwork panels are assembled by unskilled labourers to form the mould panels of the desired house plan.
STEP 2 •	Internal formwork panels are erected.   •	Window frames and block-outs are positioned within the wall cavity.  •	Reinforcing bars are positioned within the cavity to engineer specifications STEP 3 •	Door frames and block-outs are positioned within the wall cavity.  •	External formwork panels are erected to  close off the wall cavity.  •	Erection is completed in 4 hours  with 4 unskilled labourers STEP 4
The wall cavity is filled with 4m³ of moladi aerated mortar by unskilled labourers. The pour is completed in 2 hours with 4 unskilled labourers.
DAY 2 Start 07h00 Finish 17h00 STEP 5
moladi formwork panels are removed. moladi formwork panels are completely removed in 2 hours with 4 unskilled labourers.
STEP 6
Immediately after the formwork panels are removed, the walls are painted with cementitious water based paint. Oil or acrylic based paints can be applied after the walls have cured, or in 28 days.
STEP 7
The engineer certified roof is installed. The windows and doors are installed. Final finishing’s, such as sanitary ware and lighting are completed. The structure is now ready for occupation.
ADDRESS PO Box 16553 Emerald Hill Port Elizabeth South Africa 6011
CONTACT Mail: click here Phone: +27 413792600 Fax: +27 865026930
Copyright reserved © Terms of use apply
NAVIGATION
SOCIAL
moladi logo
moladi logo
moladi building system