•moladi formwork is delivered to site.Area = 74m²Mass = 550kgVolume = 4m³•moladi formwork panels are assembled byunskilled labourers to form the mould panelsof the desired house plan.
•Internal formwork panels are erected. •Window frames and block-outs are positionedwithin the wall cavity.•Reinforcing bars are positioned within the cavityto engineer specifications
•The wall cavity is filled with 4m³ of moladiaerated mortar by unskilled labourers.•The pour is completed in 2 hourswith 4 unskilled labourers.
•moladi formwork panels are removed.•moladi formwork panels are completelyremoved in 2 hours with 4 unskilled labourers.
•Immediately after the formwork panels areremoved, the walls are painted with cementitious water based paint.•Oil or acrylic based paints can be appliedafter the walls have cured, or in 28 days.
•The engineer certified roof is installed.•The windows and doors are installed.•Final finishing’s, such as sanitary wareand lighting are completed.•The structure is now ready for occupation.
•moladi formwork is delivered to site.Area = 74m²Mass = 550kgVolume = 4m³•moladi formwork panels are assembled byunskilled labourers to form the mould panelsof the desired house plan.
•The wall cavity is filled with 4m³ of moladiaerated mortar by unskilled labourers.•The pour is completed in 2 hourswith 4 unskilled labourers.
•moladi formwork panels are removed.•moladi formwork panels are completelyremoved in 2 hours with 4 unskilled labourers.
•Immediately after the formwork panels areremoved, the walls are painted with cementitious water based paint.•Oil or acrylic based paints can be appliedafter the walls have cured, or in 28 days.
•The engineer certified roof is installed.•The windows and doors are installed.•Final finishing’s, such as sanitary wareand lighting are completed.•The structure is now ready for occupation.